Thursday, May 20, 2010

Program News...

We have submitted the program description and budget for the four DDD residents who will be moving into the house.

While it isn't finalized and official yet, it is another sign that we're getting closer and closer to an opening date!

"Superior" News

We're tentatively expecting to have the foundation delivered and installed on Monday, June 7th.

Of course, weather and other factors may affect this date, but we'll provide updates as available.

Wednesday, May 5, 2010

Tuesday, May 4, 2010

Progress Report!

Prep work continues on the site... will get some pix in a day or so. Superior wall and foundation are expected to be installed soon...

The modular boxes have been ordered, and should be done in four to six weeks.

More to follow...